Below is the 2024 Street Resurfacing Map and List. This project entails 9.7 miles of street paving and 1.2 miles of alley paving with an overall budget of $2 Million. The project is expected to be completed no later than the fall of 2024.
Thornwood Crossing Potential Construction Impacts
Thornwood Crossing Bridge Project
Construction Begins: 2023
Duration: 18 Months
Construction Administrator: ODOT
Bid Amount: $15.37 Million
Funding: ODOT, City of Newark
Cherry Valley Road Bridge/Thornwood Crossing Public Involvement Meeting Information
The following are links to all documents that were presented at the Public Information Meeting held of June 22, 2016:
Downtown Newark still has many overhead electric and communication lines. These lines pose a significant health and safety hazard through the risk of fire, shock, or arc to area residents and businesses. Therefore, the City, in cooperation with AEP, has contracted with Claypool Electric to bury the lines underground in a manner consistent with current safety and building codes.
Underground infrastructure construction is complete.
Production of the final transformer needed to complete the project has been delayed. The Contractor and AEP will continue working to transfer power in the remaining section when the transformer is received, potentially late fall 2024.
The poles will be removed once communications lines have been relocated.
This project will replace the 3-span, steel beam bridge, originally constructed in 1958.
The new bridge will be a 3-span, concrete I-beam structure.
Work to begin January 2, 2024
Bridge Closes: January 22, 2024
Bridge Opens: (UPDATED): Mid-September 2024
Contractor: George J. Igel & Co., Inc.
Construction Administrator: ODOT
Bid Amount: $4.07 Million
Funding: ODOT, City of Newark
South 11th Street Improvements
(between West Main Street and Jefferson Street; including the south side of West Main Street and the North side of Jefferson Street to a location approximately 400 feet east of South 11th Street)
This project includes the following:
• Curb and gutter with inlets to improve drainage
• Sidewalk
• Resurfacing
Construction Begins: TBD
Duration: 3 Months
Construction Administrator: City of Newark
Bid Amount: $0.50 Million
Funding: Private Developer, City of Newark
The project location is West Church Street between North 29th Street and Dietrich Street. The project is an extension of the previous project completed west of North 29th Street, and will provide:
Construction Begins: 2025
Duration: 6 Months
Construction Administrator: ODOT
Estimated Cost: $2 Million
Funding: ODOT, City of Newark
This project will replace the Granville Road bridge over the Log Pond Run Diversion Channel that was originally constructed in 1980. Minor repairs were completed in 2023 to improve its structural integrity; however, it remains load restricted. The plan is to replace the existing three-span steel beam structure with a single span concrete arch culvert. This project will also include the construction of a multi-use path on the north side of Granville Road from North 21st Street to University Drive at the OSU Campus in order to improve pedestrian and cyclist safety in the area. The City has currently obtained nearly $1.8 million for construction from ODOT, and is continuing to pursue additional outside funding sources.
Construction Begins: 2026
Duration: 9 Months
Construction Administrator: ODOT
Estimated Cost: $3.2 Million
Funding: ODOT, City of Newark
Construction begins: (UPDATED) 2027
Duration: 18 Months
Construction Administrator: ODOT
Estimated Cost: $13 Million
Funding: ODOT, City of Newark
This project will reconstruct approximately 1/3-mile of roadway on Thornwood Drive, between the Railroad Tracks and Faye Drive. A single-lane modern roundabout is proposed for the Faye Drive intersection.
Construction Begins: 2026
Duration: 9 Months
Construction Administrator: Licking County TID
Estimated Cost: $4 Million
Funding: ODOT, City of Newark
The purpose of this project is to perform minor repairs to extend the expected service life of the bridge. Repairs include the replacement of expansion joints and abutment bearings, abutment patching, and road surface overlay and sealing. A Road closure will be necessary.
Construction: Summer 2025
Duration: 3 Months
Construction Administrator: City of Newark
Estimated Cost: $0.75 Million
Funding: OPWC, City of Newark
Check out the Division of Water and Wastewater construction projects.